Customization: | Available |
---|---|
Formula: | C5h10o2 |
Molecular Principal Chain: | Element Organic Polymer |
Still deciding? Get samples of US$ 2/kg
Request Sample
|
Suppliers with verified business licenses
Audited by an independent third-party inspection agency
Two Components Brushable Cold Polyurea
1. Can cure at room temperature, surface dry within 12 hours, and dry within 24 hours.
2. Excellent physical and chemical properties, with good adhesion to various substrates.Item Number | YP683/YP685 |
Solid Content % | 100 |
Work time(min) | 10-15 mins |
Surface dry time (h) | <4 |
Actual dry time(h) | <24 |
Hardness(Shore A) | 80 |
Tensile strength (MPa) | 7-8 Mpa |
Elongation at break (%) | 300 |
Tear strength | 40N/m2 |
Adhesion (pull)Mpa | 2Mpa |
1) Waterproofing protection for roofs, swimming pools, water parks, etc;
2) Production workshop anti-corrosion flooring and warehouse floor anti-corrosion and wear-resistant protection;
3) Silent floors in schools, hospitals, kindergartens, and dust-free workshop floors;
4) Can board sports venues such as basketball courts.
20kgs/drum
Sealed storage of coatings in dry, cool, and well ventilated conditions, avoiding sunlight and rain, and keeping away from sources of fire.
1. Base surface requirements: The concrete base surface should be cleaned, repaired flat, and polished to a certain roughness. Ensure that the concrete curing is completed, the strength reaches C25 or above, and the moisture content is less than 8%. After processing the base surface, the next process should be carried out as soon as possible.
2. Environmental temperature and humidity requirements: The environmental temperature at the construction site should be above 5 ºC, and construction can only be carried out when the relative humidity is less than 85%.
3. Ventilation conditions: Ventilation should be maintained during construction.
1.1 A: B=1:1 (mass ratio), solvent is not allowed to be added. Before use, pour component B into a mixing bucket and add the same mass of component A by electronic weighing in proportion. Stir thoroughly for 2-3 minutes to prevent damage Uneven mixing at the bottom of the bucket resulted in local non solidification of the floor. Ready to use and prepare, the prepared polyurea coating should be used up within 15 minutes.
1.2 During construction, first layer apply solvent-free epoxy anti-corrosion sealing primer. After the primer is completely cured, polish the area to ensure inter-layer adhesion.
Reason (note: polishing floating dust must be cleaned with a vacuum cleaner). After cleaning and polishing the floating dust, use solvent-free polyurea intermediate coating combination material to mix evenly in proportion.
1.3 Afterwards, pour this combination material onto the floor and scrape it evenly with a trowel (3mm or 5mm trowel can be selected according to thickness requirements).
After 24 hours of curing, the next process can proceed. If the construction interval exceeds 48 hours, a layer of interface agent needs to be applied before construction can proceed.
1.4 After curing, if encountering adverse weather such as rain, a layer of interface agent must be applied before proceeding to the next process.
1.5 Under normal circumstances, the coating film should be cured for at least 7 days after completion of painting to ensure optimal performance of the paint film.